About the Company
We are very proud to state that we have designed & constructed around 1600 MLD aggregate capacity STPs at various locations in India in the last 51 years. We would also like to state that our company has introduced SBR technology to India in 2005 and implemented it successfully at the first-ever SBR Plant in India with a 12.5 MLD capacity. It is located at Panaji (Goa) and is constructed for PWD, Govt. of Goa. The Plant is performing to the entire satisfaction of the client and delivering good results.
Key responsibilities
Study the tender requirements of each project during pre-tendering and post tendering stage.
Decide the technology / process to be adopted considering bid evaluation criteria / requirements of functional guarantees.
Prepare BEP including process and hydraulic dig. And layout and flow diagrams. P & IP and mass balance diag. may require depending on case to case.
Pre-Tendering stage
All above activities
Get involved with engineering team for civil, piping, mechanical, E&I costing
Give your inputs to the team as required during tilling data sheets & other documents.
Focus should be given in selecting suitable requirements for secondary treatment, BNR, disinfection, etc.
To participate and involve during detail costing by team and then briefing the tender requirements to management.
Any work as required to be carried out to get the project awarded, once we found lowest
Liaisoning with client & consultants during bid evaluation stage.
Post tendering stage
All above activities as mentioned before pre tendering stage
Prepare detailed BEP (PD, HD, LO, HFD) as per tender & confirmations given during bid evaluation stage and submit it
Get it approved from client & consultants after through compliance
To guide Engineering Team to prepare explode GAD, P&I.
To check drawing in detail for final submission.
To get it approved from client a consultant after due compliance
Any other work as required to carry out to deliver the project in time
Trial run and commissioning
To visit the site and put plant into trial run with electrical team
To stabilize the process (as selected) at site to deliver desired parameters
To monitor till commissioning & guide O&M team as & when required during entire O&M period.
Execution & Procurement stage
To guide execution team time to time as required during construction.
To guide E&M team in selecting appropriate equipment / analyzers / PLC / SCADC, etc. as required during detailed engineering stage
To perform duties as & when required & to carry out any work to deliver project in time.
Laying sewerage or, water pipelines from 250mm up to 2000mm did.
Coordinating with subcontractors, vendors local authorities
Qualifications :
ME / M Tech in Environmental / Chemical Engineering
Required Work Experience :
5+ Years of Work Experience
Work Location- Shukrawar Peth off Bajirao Road, Pune - 411002.